How long is the is the wait time to schedule a follow up Certificate of Occupancy inspection?
Two to three weeks.
Two to three weeks.
Yes, all contractor and sub information must be decided at time of submission, including all information required. The contractor must be licensed in the Town of East Hampton and all others must be Suffolk County Licensed.
Yes, two sets of plans are required, stamped and signed by an Architect or Engineer.
Pool plans must be specific for the exact pool being built and the address must be on the two (2) sets of required, stamped and signed plans.
A filled-out Demolition Permit Application must be accompanied by a shut off letter from the gas and electric companies along with a complete asbestos survey if built prior to 1974.
All pool contractors must be H26 Certified through Suffolk County.
A Building Permit is valid up to a year after the date of issuance and can be renewed at the cost of the original fee (not including the Certificate of Occupancy fee).
Permit review is usually within two to four weeks providing all required information is included when you submit.
Call 631-324-4150 and select Option 3 from the Main Menu for the East Hampton Village Building Department to schedule your inspection.
A check is required at submission and the fee is calculated as follows: 1.25% of the estimated cost $250 Certificate of Occupancy fee $750 Coastal Erosion Management Application $1,000 Demolition Permit You may also give the Building Department a call and we will calculate it for you (631) 324-4150, select 3 from Main Menu. 2023 … Continued