Herrick Park Bathroom Renovation

Details and Updates

Contractor: Carter-Melence

Architect: Botta Sferrazza Architects

Details

  • Re-shingling of the exterior of the building and the roof.
  • Impact rated glass and simpler muntin bars for the windows.
  • Installation of recess lighting inside and outside.
  • Porcelain tile for flooring and subway tile for walls.
  • All appliances (toilets, sinks, hand dryers) will be touchless, easy to use.

Estimated Completion Date: Complete!